In seeking to create great project outcomes, we also make the occasional headline. Here are the latest stories, opinions and commentary about 3L Alliance projects and related issues, from local and international media.

01 April 2021

Queens Place Construction Update-March 2021

3L Alliance and its contractor Multiplex (MPX) have continued the construction of Queen’s Place reaching a major milestone – the City Rise Apartments are now complete. Over 500 apartments are now finished.

Progress continues at Queens Place with Multiplex working on many fronts with over 320 people on site:

  • Facade panels being installed on level 68.
  • Woolworths Supermarket fit out is 95% complete and able to open later in the year.
  • Tower structure continues and is now up to level 72, only 8 levels remain.

We are in the final stretch of completing the apartments and look forward to handing over Queens Place to its new owners.

22 February 2021

Queens Place Construction Update-Jan 2021

As we kick off the new year we’ve settled almost 400 apartments at Queens Place.

Tower structure now reaches level 64 and is beginning to dominate parts of Melbourne’s the skyline.

With over 350 people on site each day Multiplex have finished apartments up to level 43 and we have been able to handover these apartment to their new owners.

Other works areas approaching completion include the Woolworths Supermarket, pool and entertainment areas and the basement areas are complete ready for purchasers cars.

Stay tuned for our next update for more wonderful photos and videos about our show rooms.

06 August 2020

英皇广场6月施工进度更新

随着英皇广场1期交割的临近,施工作业也在快速开展。公寓楼结构施工现已达到42层,俨然成为墨尔本市中心最高的公寓楼之一。
建筑商Multiplex每日在现场安排超过460名施工人员,现已完成公寓楼大堂区域、零售商户、地面层景观区域以及数间公寓的精装修。下列工作正在火热进行中:
• 零售空间:内部装修正在进行中,三联置业去年已与超市巨头签订协议入驻英皇广场商圈,预计超市将于未来12个月内开业;
• 地下室区域:整体基本完工,现正进行划线和储物区安装的工作;
• 公寓楼走廊:部分楼层的走廊装修也已完毕。设计师独具匠心,运用英皇广场Queens Place这几个字母不同排列组合勾勒出代表楼层的数字,电梯门一开数字即映入眼帘。
• 娱乐设施:健身房、游乐室以及私人用餐区等设施装修进行中;
• 28层公寓厨房、瓷砖和地毯作业正在进行;
• 公寓装修:SP1中的部分公寓已经完成内装修和瑕疵检查
• 公寓楼外部工程:外立面幕墙安装作业已经进展到38层。
更多关于样板房的精彩照片和视频请关注我们下一期的更新,敬请期待!

06 August 2020

Queens Place Construction Update-June 2020

As we approach the first settlements at Queens Place, construction is progressing at a rapid rate. Tower structure now reaches level 42 it is now one of the tallest apartment buildings in the city.
With over 460 people on site each day Multiplex have commenced final finishes in lobby areas, retail tenancies, ground floor landscaping areas and the several apartments. Other exciting work areas include:
• The retail space: where fit outs are underway with the supermarket expected to open in 12 months.
• The basement areas, which are almost complete as line marking and storage cages currently being installed.
• Apartment Corridor: the corridor fit out of some floors has also been completed. Designers ingeniously used the letters of ‘Queens Place’ to outline the numbers of floor levels; it comes into sights soon as the elevator door is opened.
• Amenity areas: such as the Gym, Games Room and Private dining areas are in the process of their fit-out.
• On level 28 apartment Kitchens, tiling and carpeting are in the process of being installed.
• Apartment Finishes: Some apartments in SP1 have completed interior decoration and defect inspection
• Externally, the façade panel installation has now reached level 38.

Stay tuned for our next update for more wonderful photos and videos about our show rooms.

28 July 2020

Queens Place Construction Update-April & May 2020

With concerted efforts, 3L Alliance and its contractor Multiplex (MPX) have continued the construction of Queen’s Place during the pandemic. Queen’s Place is being constructed by a tier 1 builder – MPX. Tier 1 contractors represent Australia’s top level of building quality. In Australia, only 6 out of 400+ contractors are in tier 1 and Multiplex is one of them.

Since the outbreak of the COVID-19 pandemic, 3L Alliance has faced unprecedented challenges and uncertainties. From the board of directors to the executive management team and all employees, the company has remained calm and resilient. All works have been actively carried out with a focus on  employees’ health. Our contractor MPX has adjusted the site construction specifications and timelines to maintain continuous construction at Queen’s Place and to complete every construction task at high quality.

Progress continues at Queens Place with Multiplex working on many fronts with over 450 people on site:

  • Facade panels being installed on the Podium levels and level 34.
  • Ground floor tenancy and lobby fit outs.
  • Supermarket fit out in the basement and carpark is almost complete.
  • Tower structure continues.
  • Lift cores at level 42.
  • Structure at level 38.
  • Fit-out works are well underway with walls and services progressing up to level 32 and kitchen joinery commenced on level 21.

Several floors have been completed. We have been able to professionally photograph some apartments to show the quality of design and finish.

20 April 2020

Queens Place Construction Update-March 2020

Progress is continuing on at Queens Place with the building starting to be visible from multiple parts of the city.

Multiplex working on many fronts including:

  • Fitout of the retail tenancies. The supermarket is set to open in approximately 12 months.
  • The basement areas are almost complete with line marking and storage cages currently being installed.
  • Apartment amenity areas – gym, games rooms and private dining areas are being fitted out.
  • Apartments being completed for inspections by 3L Alliance on level 7 and 8.
  • Apartments kitchens, tiling and carpet being installed on level 17.
  • Facade panels being installed in the tower at level 29.
  • The tower structure is currently on level 33.
  • Lift cores are up to level 37

There are almost 400 people working on site as we work up to the first round of settlements later this year.

In the coming weeks we’ll see the tower continue to grow taller and more apartments be ready for inspection.