News

In seeking to create great project outcomes, we also make the occasional headline. Here are the latest stories, opinions and commentary about 3L Alliance projects and related issues, from local and international media.

04 December 2019

Queens Place Construction Update-October and November 2019

Works continue to progress at Queens Place. Multiplex have finished the:

– Lift core at Level 21.

– Structure at Level 17

– Facade at Level 13

Other work fronts including the fit-out of the internal apartment services between levels 3 and 12, supermarket services and ground floor retail tenancies.

There are now over 180 people on site each day. Works off site include façade panels, lifts and services equipment.

04 October 2019

Queens Place Construction Update-September 2019

Fast progress continues at Queens Place with Multiplex working on many fronts:

  • Facade panels being installed to the podium and tower levels.
  • Escalator installation to retail and commercial suites
  • Basement services and preparation for fit-out works.
  • Tower structure continues on program
  • Lift cores continue on program
  • Third Tower Crane Installed to accelerate the program

In the last month several tower levels have been completed. The retail, office and supermarket tenancies are having services installed and preparation for facades. Apartment amenity areas – gym, games rooms and private dining areas are having facades and services installed.

19 September 2019

Queens Place Construction Update-August 2019

We are now into the typical tower floors and should see the building climbing at a rapid rate. Multiplex are now on level 9 with progress on many work fronts including the supermarket tenancy in the basement and podium façade panels.

The main tower lift core is on level 12 and the eastern core is complete. Ground floor areas are getting ready for facades and services. Works are being completed by over 120 people on site each day.

In the coming weeks we’ll see more facade panels, services and typical floor levels constructed as the apartments and retail areas begin to take shape.

14 August 2019

Queens Place Construction Update-July 2019

 

Multiplex have completed the podium levels at Queens Place and are about to commence the tower. The slab for the level 5 pool deck is complete as are the areas for the retail amenities.

The supermarket basement and ground floor areas are almost ready to commence their fit-out works as are the rest of the ground floor retail and lobby areas.

The main lift core is at level 10 and the podium lift core is complete.

Over 120 people continue to work at Queens Place each day.

The upcoming activities include:

– Tower apartment slabs.

– Tower lift core.

– Preparation for facade panels.

– Basement services.

In the coming months as more floors are completed, we’ll see Multiplex install the first of several thousand glass facade panels and the first apartments will take shape.

19 July 2019

Queens Place Construction Update-June 2019

Works are continuing at Queens Place with Multiplex progressing on many fronts:

– Basement services and preparation for fit-out works.

– Podium structure

– Lift cores – currently at level 8.

In the last month several podium levels have been completed and feature fins have been installed. The retail, office and supermarket tenancies are taking shape as are the apartment amenity areas – gym, games rooms and private dining areas.

There are over 120 people on site each day. Works off site include façade panels, lifts and services equipment. In the coming months we’ll see the first facade panels installed and level 5 pool areas take shape.

13 June 2019

Queens Place Construction Update-May 2019

The podium levels at Queens Place continue to take shape with Multiplex currently constructing the level 2 slab.

The two lift cores are at level 6, well above street level and visible from the nearby streets.

Manpower continues to increase with structural and services trades being the majority of the 130 people on site. The apartment lobbies, retail area and office tenancies are taking shape as is the central atrium space.

In the coming month we’ll see the podium fins installed and the preparation for the facade panels.